Upstream

installation/fabrication

Project Overview
  • Build Production Module. Fabricate three decks all legs and stack. Install all Vessels. Fabricate and install all piping Carbon, Stainless, and Super Duplex.
  • Load on Barge and Tie down on Barge heading to Devils Tower.
project details
  • 380 ton production module package
  • 77,000 man-hours on the project, with day & night shifts, incident-free performance
  • Repair rate of less than 1%
  • On-schedule load-out, even with revisions coming in as late as 2 days before load-out