Build Production Module. Fabricate three decks all legs and stack. Install all Vessels. Fabricate and install all piping Carbon, Stainless, and Super Duplex.
Load on Barge and Tie down on Barge heading to Devils Tower.
project details
380 ton production module package
77,000 man-hours on the project, with day & night shifts, incident-free performance
Repair rate of less than 1%
On-schedule load-out, even with revisions coming in as late as 2 days before load-out