Upstream

2016 tar

Project Overview
  • 553 flange joints, 112 valves, 70 Spools
  • 53 leak/service tests successfully completed with no leaks on TAR related joints
  • Over 40 vendors and 380 individuals involved with the TAR
  • Total of 135 work packs
  • 150 ICC’s, 790 WCC’s executed
  • 125 Lift plans
  • Total of 116 welds completed –ZERO repairs
  • 1108 “A” ITR’s and 144 “B” ITR’s completed
  • 77 MC1’s completed
  • 42 SH1’s completed
  • 30 MOC’s startup authorized
notable achievements

Replacement of Oil SDV 41701 to allow ILI pigging campaign

  • 76 CUL repairs (66 extra work packs)
  • Regulatory compliance scope
  • Integrity Management inspections and repairs
  • 19,820 actual MH’s executed (14,262 execution phase)
    -881 discovery scope man-hours executed (including Launcher, SW outage, E-Gen)
  • Significant discovery–Emergency Generator failure, SW outage schedule w/T-Gen#3, Launcher flange leak, CuNi spool corrosion