Upstream
2016 tar
Project Overview
- 553 flange joints, 112 valves, 70 Spools
- 53 leak/service tests successfully completed with no leaks on TAR related joints
- Over 40 vendors and 380 individuals involved with the TAR
- Total of 135 work packs
- 150 ICC’s, 790 WCC’s executed
- 125 Lift plans
- Total of 116 welds completed –ZERO repairs
- 1108 “A” ITR’s and 144 “B” ITR’s completed
- 77 MC1’s completed
- 42 SH1’s completed
- 30 MOC’s startup authorized
notable achievements
Replacement of Oil SDV 41701 to allow ILI pigging campaign
- 76 CUL repairs (66 extra work packs)
- Regulatory compliance scope
- Integrity Management inspections and repairs
- 19,820 actual MH’s executed (14,262 execution phase)
-881 discovery scope man-hours executed (including Launcher, SW outage, E-Gen) - Significant discovery–Emergency Generator failure, SW outage schedule w/T-Gen#3, Launcher flange leak, CuNi spool corrosion