Power Generation

anson 1

Project Overview
  • We were initially the second mechanical contractor selected to improv e the schedule about six months into the project. On the plains of Texas, we partnered with Engie to provide 200+ installers and over 50 electrical installers and cut an additional six months out of the proposed schedule. The project was name-plated 200 MW AC with 70 inverters and over 800,000 modules to install. Discovery completed 58 of the 70 sub-arrays for mechanical installation. We also installed and connected three of the eight medium voltage circuits as well as the DC collection in those same circuits. 682,000 modules and over four miles of cable later we successfully completed the project on time.

Service Lines
Service Line PDF's